Yes, the ESA is a permitting law and a major cause of permitting problems
Photo Credit: Getty
Over the last several weeks, strong disagreement over the Bipartisan American Affordability and Jobs Act (BAAJA) has emerged. Some groups say that the bill will help streamline the environmental review and permitting process, while others say it will lead to environmental disaster.
The permitting bill, which passed the Senate on November 19, is almost 500 pages long and touches on several statutes involved in the permitting process. The Endangered Species Act (ESA) is one statute that is reformed, but some groups are saying that the ESA doesn’t belong in any permitting package. For example, one environmental group recently stated in a Politico email newsletter that the ESA “is not one of the underlying causes of permitting delays.”
To decide whether this is true, it’s important to know that the ESA itself does, in fact, have permitting provisions. One of those provisions is found in Section 10 of the law. In short, the ESA prohibits actions that result in the “taking” of an endangered species. However, if the “taking” is “incidental to, and not the purpose of” the action, then an Incidental Take Permit (ITP) may be awarded under certain conditions. In other words, you can’t intentionally shoot an endangered species, but if you want to build a house and an endangered species happens to be nearby, you will likely need an ITP.
Another permitting process is found in Section 7 of the ESA. Federal agency actions that may affect listed species or critical habitat must go through a consultation process and get approval from one of the ESA’s implementing agencies. For example, water supply projects undertaken by the US Army Corps of Engineers must first go through consultation with, and get approval from, either the Fish and Wildlife Service (FWS) or the National Marine Fisheries Service to ensure that the project will not jeopardize any listed species or their habitat.
Now that we’ve established the ESA is a permitting law, does it cause permitting delays? A study published last month in the Journal of Public Economics indicates that it does, as discussed by the author in an article on Substack:
[T]he ESA has reduced US housing stock by around 6.3 million units since 1980, which is about 4% of 2025 housing stock. Without the several hundred ESA listings since 1980, the US would be permitting hundreds of thousands of additional units annually with gains concentrated in major metro areas and especially coastal California.
Given that the US is in the midst of a housing crisis, these findings are especially important.
There are many other examples of the ESA causing delays. For example, in one particular timber harvesting and housing development project, the ITP applicants waited for 16 years before challenging the FWS’s inaction on the application.
The China Mountain wind farm is another example of a project that got caught up in ESA permitting delays. In 2014, the Bureau of Land Management suspended the permitting process due to FWS considering the listing of the sage grouse as endangered under the ESA. As a result, the renewable energy company proposing the project (RES America) decided not to pursue it further. A 2014 New York Times article explained that the China Mountain wind farm was just one of more than two dozen energy project permits in the West that were delayed, altered, or denied because of the sage grouse.
The delta smelt, a small fish native to California’s Sacramento–San Joaquin River Delta, is another ESA-listed species that has wreaked permitting havoc. As explained by Megan Jenkins and John Nagle from the Pacific Legal Foundation:
In a 2008 biological opinion, the U.S. Fish and Wildlife Service (FWS) concluded that two major water projects that deliver water from the Delta to California’s agriculture-rich Central Valley needed to reduce operations substantially to protect the endangered fish.
Yet another study found that the median cost of large-scale Habitat Conservation Plans, which are submitted as part of the ITP application, was over $100 million. Such a high compliance cost likely drives some applicants to risk pursuing their project without ever applying for an ITP in hopes that they don’t get caught. Still others might be driven to shoot, shovel, and shut up.
There is no question that the ESA is, in fact, a permitting law. There is also no question that the ESA’s permitting provisions have created significant problems. Evidence suggests that applying for a permit is expensive and can take over a decade. Not only do ESA reforms rightly belong in a permitting package, but they are also necessary.